Progress this month
- More deliveries - 03/08/07
- The Titan Rainwater Harvesting Tank is installed - 06/08/07
- Work Begins on the Access Road - 22/08/07
- The Soak Away - 23/08/07
- Work Continues on the Access Road - 23/08/07
The Titan Rainwater Harvesting Tank is installed - 06/08/07





- Click to enlarge
- Full photo gallery »
An exciting day as the Titan rainwater harvesting tank is manoeuvred into position, filled with water and the trench is backfilled. The tank had to be filled with water to secure it in the trench and stop it from floating when the trench was backfilled.
The Titan rainwater harvesting tank will use the rainwater from the roof, filter out any debris and leaves and store the water in the tank until it is needed. When needed the water will be drawn off using a silent pump and then filtered before being used to flush the toilets in the Sustainable Building Center.
Further details of the product can be found in the Drainage and Water Conservation section of this website.