Progress this month
- Boarding the roof - 01/02/08
- Delivery of the Pilkington Glazing- 06/02/08
- The installation of the glazing begins- 20/02/08
- Further glazing is fitted - 22/02/08
- Delivery of Insulation - 28/02/08
Delivery of the Pilkington Glazing -6th of February, 2008





- Click to enlarge
- Full photo gallery »
The Pilkington Glazing is delivered to site ready to be fitted into the curtain walling on the south side of the building.
The roof is a hive of activity as it is boarded and further beams are fixed into place. The Kerto beams are fitted over the courtyard area at the front of the building and provide a dramatic entrance.
Kerto has more load-carrying capacity than most of the traditional wooden materials. Kerto is stronger, straighter, lighter and more stabile than commercial sawn timber. With its great flexibility, Kerto has many uses within the construction and industrial markets, including new buildings, renovation and repair, and the manufacturing of prefabricated components.