Progress this month
- Boarding the roof - 01/02/08
- Delivery of the Pilkington Glazing- 06/02/08
- The installation of the glazing begins- 20/02/08
- Further glazing is fitted - 22/02/08
- Delivery of Insulation - 28/02/08
Further glazing is fitted -22nd of February, 2008





- Click to enlarge
- Full photo gallery »
The Pilkington Activ™ Suncool glass is fitted in to the rest of the curtain walling on the south side of the building. The building is beginning to take shape and become water tight so that the internal decoration can commence.
The mock up roof on the north side of the building is fitted with photovoltaic tiles ready for the installation of the solar thermal panels.