Progress this month
- Work Begins - 01/06/07
- Site Preparation - 04/06/07
- HV Cable - 04/06/07
- First Delivery Vehicle On Site - 06/06/07
- Ground Works Begin - 12/06/07
- North Wing Foundations - 15/06/07
- South Wing Foundations - 18/06/07
- After the Floods - 25/06/07
After The Floods - 25/06/07





- Click to enlarge
- Full photo gallery »
The progress continues this week with further development in extending the foundations of the Southern Wing and the base of the Northern Wing becoming very apparent. The progress has been admirable in the face of the extreme weather conditions which have caused severe flooding in various parts of the country. The evidence on site can be seen with several large pools, SBC team member Siobhan Smith can be seen testing the depth in her safety wellies!
Wolseley deliveries are now commonplace with Brandon Hire visiting the site on the day these shots were taken.