[« Previous] [Next »]
Progress this month
- Work Begins - 01/06/07
- Site Preparation - 04/06/07
- HV Cable - 04/06/07
- First Delivery Vehicle On Site - 06/06/07
- Ground Works Begin - 12/06/07
- North Wing Foundations - 15/06/07
- South Wing Foundations - 18/06/07
- After the Floods - 25/06/07
First Delivery Vehicle On Site - 06/06/07

- Click to enlarge
- Full photo gallery »
Fittingly enough, the first delivery vehicle on site on 4 June was a Build Center wagon from nearby Kenilworth branch, the first of many visits to be made over the coming months.