Progress this month
- Work Begins - 01/06/07
- Site Preparation - 04/06/07
- HV Cable - 04/06/07
- First Delivery Vehicle On Site - 06/06/07
- Ground Works Begin - 12/06/07
- North Wing Foundations - 15/06/07
- South Wing Foundations - 18/06/07
- After the Floods - 25/06/07
HV Cable - 04/06/07




- Click to enlarge
- Full photo gallery »
The build programme requires the diversion of a HV cable and the work for Eon through their sub contractor Alfred McAlpine started in week commencing 4 June. The photographs show the trench dug for the diversion and the materials awaiting installation.