Progress this month
- Work Begins - 01/06/07
- Site Preparation - 04/06/07
- HV Cable - 04/06/07
- First Delivery Vehicle On Site - 06/06/07
- Ground Works Begin - 12/06/07
- North Wing Foundations - 15/06/07
- South Wing Foundations - 18/06/07
- After the Floods - 25/06/07
North Wing Foundations - 15/06/07





- Click to enlarge
- Full photo gallery »
The foundations for the North wing are now filled and the reinforcement in place despite heavy rainfall which caused flooding in some parts of Leamington.