Progress this month
- Knauf Glasswool 03/03/08
- Marshalls Priora Paving is laid- 05/03/08
- The NBT Claytec walls are constructed- 06/03/08
- Gabion Walls - 11/03/08
- Work continues on courtyard roof - 12/03/08
- Passivent Airstract Terminals - 13/03/08
- Solar Cylinders - 17/03/08
- Insulation cutaways - 19/03/08
- Filling of the Gabion Cages - 20/03/08
- Glulam Beams - 25/03/08
- Photovoltaics - 27/03/08
- 31st March - 31/03/08
Marshalls Priora Paving is laid - 5th of March, 2008





- Click to enlarge
- Full photo gallery »
Further areas of Marshalls Priora paving are laid on site to complete the footpaths and walkways. The Priora paving is porous which is compliant with the SUD’s system which has been installed on site. The paving will reduce pooling and will allow the water to penetrate the surface and drain down into the ground below.
The installation of the Knauf Glasswool and the Pilkington Activ™ Suncool glazing is continued on the Southern gallery area.