Progress this month
- Knauf Glasswool 03/03/08
- Marshalls Priora Paving is laid- 05/03/08
- The NBT Claytec walls are constructed- 06/03/08
- Gabion Walls - 11/03/08
- Work continues on courtyard roof - 12/03/08
- Passivent Airstract Terminals - 13/03/08
- Solar Cylinders - 17/03/08
- Insulation cutaways - 19/03/08
- Filling of the Gabion Cages - 20/03/08
- Glulam Beams - 25/03/08
- Photovoltaics - 27/03/08
- 31st March - 31/03/08
Glulam Beams - 25th of March, 2008





- Click to enlarge
- Full photo gallery »
The Finnforest Glulam beams that support the flying roof are fitted. The roof which creates a covered courtyard area is supported by just two huge Glulam Beams which are essentially a laminated product from PEFC certified wood sources.
The Gabion wall is finished along the front of gallery.