Progress this month
- The Northern Walls are made Watertight - 02/11/07
- The Worcester Heat Pump Collectors Arrive - 09/11/07
- The Korklite Insulation is Delivered - 13/11/07
- The Korklite Insulation is Fitted - 14/11/07
- The first delivery from Electric Center - 20/11/07
The Northern Walls are made Watertight - 02/11/07





- Click to enlarge
- Full photo gallery »
The north side of the building is made watertight with the application of a weatherproof barrier on the exterior walls. The roof is also boarded up with PEFC certified plywood ready for the roofing team to begin work.
On the south side of the building the first floor Hanson Twin wall is fitted into place with the help of the crane.
The Rockwool insulation which will be used for the flooring within the building arrives on site.