- The Northern Walls are made Watertight - 02/11/07
- The Worcester Heat Pump Collectors Arrive - 09/11/07
- The Korklite Insulation is Delivered - 13/11/07
- The Korklite Insulation is Fitted - 14/11/07
- The first delivery from Electric Center - 20/11/07
The Worcester Heat Pump Collectors Arrive - 09/11/07





- Click to enlarge
- Full photo gallery »
The Worcester ground source heat pump collects are delivered to site and fitted into the trench dug to the east of the building. The collectors are laid on a bed of sand at a calculated angle.
Inside the building the Rockwool insulation is beginning to be laid on the north side. The south side roof has been boarded up ready for it to be insulated and weatherproofed before the sedum is planted.