Progress this month
- Rockwool Flexi Insulation and the delivery of the Priora Paving - 02/10/07
- Laying the Marshalls Priora Paving - 04/10/07
- Timber Frame - 11/10/07
- The Arrival of Hanson Cobiax - 12/10/07
- The Hanson Cobiax Floor - 12/10/07
- Fitting the Finnforest I Beams - 15/10/07
- The completion of the Roof Joists - 19/10/07
- Steel Enforcement for the Cobiax Slab - 22/10/07
- The Pouring of the Concrete - 24/10/07
- The Completion of the Cobiax Slab - 24/10/07
- Development of the North Side - 30/10/07
The Arrival of Hanson Cobiax - 12/10/07





- Click to enlarge
- Full photo gallery »
Cobiax is being used in the construction of the first floor in the south side gallery to allow for wider spans without support columns. Cobiax arrives on site as precast concrete slabs with cages of hollow plastic spheres fixed on top to reduce the amount of concrete that needs to be used for the flooring. The slab weight is reduced by 35% by including the plastic spheres which fill the non structural space. This reduced slab weight allows for the wider spans without the need for support columns which can take up valuable space.
One of the main advantages of using Cobiax is that far less concrete is needed and with concrete production being a very energy intensive process this is a great move towards a more sustainable building. There are many other advantages such as a reduced cost due to a volume reduction and reduced bracing, lower transport costs and quick installation.