Progress this month
- Rockwool Flexi Insulation and the delivery of the Priora Paving - 02/10/07
- Laying the Marshalls Priora Paving - 04/10/07
- Timber Frame - 11/10/07
- The Arrival of Hanson Cobiax - 12/10/07
- The Hanson Cobiax Floor - 12/10/07
- Fitting the Finnforest I Beams - 15/10/07
- The completion of the Roof Joists - 19/10/07
- Steel Enforcement for the Cobiax Slab - 22/10/07
- The Pouring of the Concrete - 24/10/07
- The Completion of the Cobiax Slab - 24/10/07
- Development of the North Side - 30/10/07
The Pouring of the Concrete- 24/10/07





- Click to enlarge
- Full photo gallery »
The concrete was poured on to the Cobiax slab to complete the first floor structure of the south side of the building. The Concrete was poured directly on to the plastic spheres and the steel frame and then spread out so that it filled all the spaces between the spheres.