Progress this month
- Beam and Block Floor - 06/09/07
- Completion of Beam and Block Floor - 17/09/07
- The start of the installation of the Finnjoists - 24/09/07
- The Hanson Twin Wall Arrives - 26/09/07
- Fixing of the Finnjoists and Hanson Twin Wall - 28/09/07
Completion of Beam and Block Floor - 17/09/07





- Click to enlarge
- Full photo gallery »
With the beam and block floor complete the materials for the next phase of construction arrive on site and, in particular, the Finnforest Finnjoists which will be integral to the structure of the Northern Wing. Work has also started on the access road and hardstandings which will be integrated into the site-wide sustainable urban drainage system.
The scaffolding to facilitate the next phase has also begun to appear on site.