Progress this month
- Beam and Block Floor - 06/09/07
- Completion of Beam and Block Floor - 17/09/07
- The start of the installation of the Finnjoists - 24/09/07
- The Hanson Twin Wall Arrives - 26/09/07
- Fixing of the Finnjoists and Hanson Twin Wall - 28/09/07
The start of the installation of the Finnjoists - 24/09/07




- Click to enlarge
- Full photo gallery »
Work commenced on the installation of the Finnjoists which are being used innovatively as wall joists utilising their superb performance characteristics. The products are manufactured by Wolseley supply partner Finnforest and carry full PEFC certification. The installation is moving rapidly as the onsite team integrate the products with the sub-structure to form the now familiar sweeping curves of the North Wing of the building.