Progress this month
- Beam and Block Floor - 06/09/07
- Completion of Beam and Block Floor - 17/09/07
- The start of the installation of the Finnjoists - 24/09/07
- The Hanson Twin Wall Arrives - 26/09/07
- Fixing of the Finnjoists and Hanson Twin Wall - 28/09/07
The Hanson Twin Wall Arrives - 26/09/07





- Click to enlarge
- Full photo gallery »
While progress continues on the north side of the building with the construction of the finnframe, the Hanson Twin Wall which will be fitted into the South Wing is delivered to site.